How long does a kitchen remodel take in Austin?

Five to eleven weeks on site, depending on how much changes, plus two to six weeks beforehand for design, pricing and permits. Here is the timeline step by step, and what actually stretches it.

Newhall Lane kitchen remodel with a quartz island and brass pendants, Austin, TX

A kitchen remodel in Austin takes five to seven weeks on site when the layout stays the same, seven to ten weeks when walls or plumbing move, and eight to eleven weeks with full custom millwork. Add two to six weeks before anyone swings a hammer for design, pricing and the City of Austin permit. From first call to cooking dinner, most families should plan on two to four months.

Those are the numbers from Prime Construction & Remodeling’s completed kitchens in Austin and the hill country, and they match what we publish on our kitchen remodeling page. A typical kitchen renovation can take anywhere from five weeks to three months on site, depending on the scope of the project. The rest of this guide walks through the timeline step by step, from start to finish, and explains why one homeowner’s new kitchen finishes on time while the one down the street runs two months long.

Kitchen remodel timeline by scope

The single biggest factor in how long a kitchen remodel takes is not the size of the room. It is how much of the room changes behind the finishes.

ScopeBefore work startsOn siteTypical price range
Same footprint — new cabinets, counters, appliances, lighting; plumbing stays put2–4 weeks5–7 weeks$42,500–$90,000
Layout change — wall removed, sink or range relocated4–6 weeks7–10 weeks$77,500–$130,000
Layout change + full custom — custom millwork, premium stone and appliances4–6 weeks8–11 weeks$110,000–$175,000

Price ranges are from our Austin kitchen remodel cost guide. They are where most projects land, not a ceiling.

The kitchen renovation timeline, step by step

Every kitchen we build follows the same order. Knowing it helps you see which weeks you control and which ones you don’t.

1. Walkthrough (day one)

We measure, check whether the wall you want gone is load-bearing, and look for signs of what sits behind the finishes. You leave with a realistic price range that day. There is no charge for this visit.

2. Design and selections (two to six weeks)

Kitchen design comes first: drawings, the kitchen layout, cabinet line and door style, cabinet hardware, and every selection: countertop, tile, plumbing fixtures, appliances and lighting. If you want a new kitchen island or a different footprint, it is decided here. This is the stage you control most. Late selections are the most common reason a kitchen remodel runs long, because cabinets and appliances are ordered off them.

3. Permits (runs alongside design)

Replacing cabinets and finishes does not need a building permit in Austin. Moving plumbing, altering gas, changing electrical circuits or removing a wall does. Permitted work is filed through the City of Austin’s Austin Build + Connect (AB+C) portal. As of July 2026 the city targets ten business days for residential plan review; structural work often draws comments and a resubmittal.

4. Demolition and protection (first week on site)

A sealed dust wall goes up, floors are protected on the route in and out, and a temporary kitchen is set up elsewhere in the house. Tear-out itself takes days, not weeks.

5. Rough-in and inspection (one to three weeks)

New plumbing, gas, electrical circuits, lighting and ventilation run inside the open walls. Changing or adding electrical or plumbing is what makes this stage take longer than people expect. If a wall came out, the beam and posts go in here. The city inspector checks that everything is up to code before the walls close. A layout change spends most of its extra time in this stage.

6. Drywall, cabinets and countertops (two to four weeks)

Walls are closed and finished, cabinets are installed and leveled, and then the countertops are templated off the installed cabinets. Stone is cut to that template, so there is a gap of days between templating and install that no crew can skip.

7. Backsplash, fixtures, appliances and punch list (one to two weeks)

Tile, plumbing fixtures, appliances, lighting trim and hardware. Then we walk the kitchen with you, fix every item on the punch list, and hand over the warranty in writing.

Why does a kitchen remodel take so long?

Most of the time in a kitchen remodel isn’t the work itself. It is waiting on decisions, materials and inspections that have to happen in order. These are the four things that stretch a kitchen remodel in Austin:

  • Selections that arrive late. Cabinets can’t be ordered until the layout and door style are final, and nothing after cabinets can start without them.
  • Cabinet lead time. Semi-custom and custom cabinetry is built to order. Our custom vs. semi-custom cabinets guide explains the trade-off.
  • What is behind the walls. We find something in roughly one kitchen in four — cast iron drain lines, undersized electrical, or water damage under a window. In a house built before 1990, hold back 10 to 15 percent of the budget for it.
  • A load-bearing wall. Removing one means an engineered beam, posts down to the foundation, and often new footing work. It adds inspection steps and usually a permit review comment.

Outside the City of Austin the clock can differ. West Lake Hills and Rollingwood run their own building departments with their own timelines, and an HOA approval can add weeks before the permit is even filed.

How long does a small kitchen remodel take?

A small kitchen saves less time than people expect. Cabinets, counters, plumbing, inspections and appliance delivery take about the same number of steps in a 120 square foot galley as in a 300 square foot kitchen. A small same-footprint kitchen still sits at the low end of five to seven weeks on site. Square footage is the wrong measure for kitchens, both for time and for price. Remodeling your kitchen in stages, or redoing the entire kitchen at once, changes the timeline far more than its size.

Is a kitchen remodel worth the time?

For most families who plan to stay, yes: it is the room used most every day. If you are thinking about resale, a smaller refresh usually returns more of its cost than a full layout change. Our guide to the 30% rule for renovations shows how to size a kitchen budget against your home’s value.

How to keep a kitchen remodel on schedule

  • Make every selection before demolition, on the dated schedule your builder gives you at contract.
  • Decide early whether any wall is coming out, so the engineer and the permit are done before the start date.
  • Ask for a weekly written update with photographs. We send one on every job without being asked.
  • Agree up front how surprises are handled: same-day photographs, options and a written price, approved by you before work continues.
  • Keep the budget contingency separate, so a discovery doesn’t stop the job while you find the money.

Most clients live at home through a kitchen remodel. Our guide on living in your house during a renovation covers how to make the weeks without a kitchen bearable.

A real example: a relocated kitchen in Northwest Hills

On Valburn Drive in Northwest Hills, Prime Construction & Remodeling moved the kitchen to a new spot in the house. That is the layout-change tier: plumbing, electrical and venting all rerouted, inspected, and then the cabinetry built around the new plan. Projects like this sit in the seven to ten week range on site.

Frequently asked questions

How long does it take to rip out and replace a kitchen?

Five to seven weeks on site if the layout stays the same. The tear-out itself takes days; the rest is rough-in, inspection, cabinets, countertop templating and finishes, which have to happen in order.

How long does a full kitchen remodel take?

Seven to ten weeks on site when walls or plumbing move, and eight to eleven weeks with full custom millwork, plus two to six weeks beforehand for design, pricing and permits.

Do I need a permit to remodel my kitchen in Austin?

Not for replacing cabinets and finishes. Yes for moving plumbing, altering gas, changing electrical circuits or removing a wall. Permitted work goes through the City of Austin AB+C portal.

What delays a kitchen remodel the most?

Late selections. Cabinets are ordered from the final layout and door style, and every step after cabinets waits on them. Hidden conditions behind the walls are the second most common cause.

Can I live in my house during a kitchen remodel?

Most of our clients do. A dust wall seals the kitchen off, a temporary kitchen is set up elsewhere in the house, and the crew uses a protected route in and out.

Is $30,000 enough for a kitchen remodel in Austin?

It is below our published range, which starts at $42,500 for a same-footprint kitchen with new cabinets, counters and appliances. Thirty thousand dollars can cover a refresh such as new counters, paint and fixtures on existing cabinets.

Next

Want a timeline for your kitchen?

We will walk the kitchen, tell you which tier it falls in, and give you a realistic range for both the schedule and the price, the same day.

Who wrote this

Prime Construction & Remodeling

A design-build remodeler at 705 N Bluff Dr in South Austin, founded in 2013 by Jesse Dadon. Kitchens, bathrooms, additions, ADUs and whole-home renovations across Austin and the hill country. NARI member, 5.0 from 200+ Google reviews.

Straight to a person

(512) 948-9398

One office, one number. We answer every message ourselves, the same business day during work hours.

Two years on workmanship · lifetime warranty on our shower pans · free first walkthrough